Wastewater Treatment Plant

Die-Casting

Project Overview :

Design capacity : 12m3 /Hour
Wastewater : Die-Casting
Operation :24 Hrs
Die-Casting Wastewater treatment plant to treat industrial effluent from the manufacturing facility to meet Malaysian EQA DOE discharge standard A regulation 2009.

Objectives :

Achieve treated effluent quality meeting EQA DOE discharge limits for BOD, COD, SS, Aluminium, Fluoride and oil & grease.

Scope of Work :

Civil, mechanical, electrical, instrumentation & to obtain DOE Approval.

Key Features/Process Flow:

Chemical & Bio logical treatment

Timeline :

3 - 4 months (Permits, Design, Procurement, Construction & commissioning)

Rubber Glove

Project Overview :

Design capacity : 15m3 /Hour
Wastewater : Rubber Glove
Operation :24 Hrs
Wastewater treatment plant to treat industrial effluent from the manufacturing facility to meet Malaysian EQA DOE discharge standard B regulation 2009.

Objectives :

Achieve treated effluent quality meeting EQA DOE discharge limits for BOD, COD, SS, Ammoniacal Nitrogen and oil & grease.

Scope of Work :

Civil, mechanical, electrical, instrumentation & to obtain DOE Approval.

Key Features/Process Flow:

Chemical & Bio logical treatment

Timeline :

3 - 4 months (Permits, Design, Procurement, Construction & commissioning)

Powder Coating

Project Overview :

Design capacity : 3m3 /Hour
Wastewater : Powder Coating
Operation : 8 Hrs
Wastewater treatment plant to treat industrial effluent from the manufacturing facility to meet Malaysian EQA DOE discharge standard A regulation 2009.

Objectives :

Achieve treated effluent quality meeting EQA DOE discharge limits for BOD, COD, SS, Al, Cr+3 and oil & grease.

Scope of Work :

Civil, mechanical, electrical, instrumentation & to obtain DOE Approval.

Key Features/Process Flow:

Chemical treatment

Timeline :

3 - 4 months (Permits, Design, Procurement, Construction & commissioning)

Shampooing Sector

Project Overview :

Design capacity : 2m3 /Hour
Wastewater : Shampoo, Shower Gel & Others
Operation : 24 Hrs
Wastewater treatment plant to treat industrial effluent from the manufacturing facility to meet Malaysian EQA DOE discharge standard B regulation 2009.

Objectives :

Achieve treated effluent quality meeting EQA DOE discharge limits for BOD, COD, SS, Al, Cr+3 and oil & grease.

Scope of Work :

Civil, mechanical, electrical, instrumentation & to obtain DOE Approval.

Key Features/Process Flow:

Chemical & Bio logical treatment

Timeline :

3 - 4 months (Permits, Design, Procurement, Construction & commissioning)

Food Industries

Project Overview :

Design capacity : 0.55m3 /Hour
Wastewater : Food Industries
Operation : 8 Hrs
Wastewater treatment plant to treat industrial effluent from the manufacturing facility to meet Malaysian EQA DOE discharge standard A regulation 2009

Design capacity :

0.55m3 / Hour

Wastewater :

Food Industries

Operation :

24 Hrs

Scope of Work :

Civil, mechanical, electrical, instrumentation & to obtain DOE Approval.

Timeline :

3 - 4 months (Permits, Design, Procurement, Construction & commissioning)

Objectives :

Achieve treated effluent quality meeting EQA DOE discharge limits for BOD, COD, SS, Cr+3 and oil & grease.

Key Features/Process Flow:

Chemical treatment

Location

Map Location